The story
In 2001, a dedicated busway transit project was judged to be the most cost-effective way of relieving congestion on Interstate 84 between Hartford, West Hartford, Newington and New Britain. The 9.4-mile (15.1 km) line was projected to cost $570 million, of which $400 million was funded by federal grants.
The project officially broke ground on May 22, 2012 and opened to the public on March 28, 2015.
Proof of payment is used for fare collection along the route. On June 23, 2015, CTDOT began issuing $75 tickets for riders found to have not paid their fare.
Preliminary work estimated a $10 million annual cost of running the various CTfastrak routes and new feeder services. In September 2015, CTtransit released that the yearly cost would be substantially higher at $17.5 million.
In October 2019, the state applied for a federal grant to test autonomous buses on the CTfastrak busway beginning in 2020.
As of August 25, 2024, CTfastrak added Route 125 as a connection between Downtown Hartford, Newington, and the Berlin Turnpike.
Hartford Line
The Hartford Line commuter rail service between New Haven, Connecticut and Springfield, Massachusetts via Hartford commenced on June 16, 2018. It initially connects to CTfastrak at Union Station. Hartford Line stations adjacent to the CTfastrak stops at West Hartford (Flatbush Avenue) and Newington Junction are planned to open later.
The 2012 environmental assessment for the Hartford Line included preliminary plans for four infill stations including West Hartford and Newington Junction; although they were not yet funded, this would allow future planning and construction to be expedited. On January 12, 2015, the state announced that $5.75 million in funding would be made available for environmental mitigation and design at ten Hartford Line and New Haven Line stations, including design funding for Hartford Line platforms at West Hartford and Newington Junction.
Read the full text
CTfastrak East
Planning began in early 2016 for extending CTfastrak service to communities east of Hartford. The expansion would incorporate many of the BRT features of the existing system, including branded buses, large shelters, real-time information, and frequent all-day service. However, it would run on existing HOV lanes on I-84 and I-384 rather than a dedicated busway.