The Greek government established Elliniko Metro as Attiko Metro (Greek: Αττικό Μετρό) on 18 July 1991, under Law 1955/1991. The original purpose of Attiko Metro was to oversee the delivery of the Base Project of the Athens Metro, whose contract had been awarded to the Olympic Metro consortium of 23 companies in the previous month. The Base Project consisted of two lines with a total length of 17.6 kilometres (10.9 miles) and 20 stations, and opened in three phases from 28 January 2000 to 22 April 2003. The Greek government then assigned Attiko Metro the role of developing and build the Thessaloniki Metro in December 2003, and any future extensions to the Athens Tram in 2013.
On 18 May 2023, Greek Prime Minister Kyriakos Mitsotakis announced that in advance of the opening of the Thessaloniki Metro in 2024, Attiko Metro would change its name to Elliniko Metro.
Timeline of Athens Metro projects
In this table, the completion date refers to the opening of the last section or station in the contract: for example, the initial scheme of the Athens Metro opened in three stages, on 28 January 2000, 15 November 2000, and 22 April 2003.
From Wikipedia’s article on Elliniko Metro, shared under CC BY-SA 4.0.4